Vikramshila Setu Repair Nears Finish: January 30 Handover Target

Vikramshila Setu Repair Nears Finish: January 30 Handover Target

Restoration work on Bhagalpur's vital Vikramshila Bridge (Vikramshila Setu) has cleared a decisive engineering milestone, with steel truss girders now fitted across all four damaged sections and authorities targeting handover by January 30, 2027, ahead of a mandatory full load test. During an on-site inspection on Sunday, November 29, 2026, Bihar Road Construction Minister Engineer Kumar Shailendra reviewed progress alongside officials from the Bridge Construction Corporation and SP Singla Construction Company, instructing teams to keep the remaining work strictly on schedule. The minister confirmed that about 90 percent of work is complete on the two damaged sections at the Navgachhia end and 70 to 75 percent at the Bhagalpur end, while reassuring commuters and transporters that the upgraded steel truss spans retain the bridge's 70-ton load capacity—matching the original design and strengthening overall durability. Across Uttar Pradesh—especially in state capital Lucknow and neighboring eastern-corridor hubs such as Unnao, Kanpur, Prayagraj, and Varanasi, where interstate freight, rail-road logistics, and major Ganga river-bridge upgrades connecting UP and Bihar carry major economic relevance—steady progress on the Vikramshila link signals smoother regional movement ahead.

Vikramshila Bridge Repair Progress and Technical Scorecard

Work Component / Parameter Current Status & Engineering Details
Steel Truss Girder Installation Completed across all four damaged sections of the bridge
Navgachhia End Progress Roughly 90% work completed across the two damaged sections on the Navgachhia side
Bhagalpur End Progress Roughly 70% to 75% work completed across the two damaged sections on the Bhagalpur side
Expansion Joints & Bearings 20 of 67 damaged expansion joints replaced so far, alongside rapid replacement of ball bearings
Design Load Capacity 70 tons—matching the original bridge specification so heavy vehicles face no structural ambiguity once cleared
Handover & Reopening Protocol Handover targeted by January 30 (in line with Chief Minister Samrat Chaudhary's announcement), followed by a full load test before opening to vehicular traffic

Inside Minister Kumar Shailendra's Site Inspection and Load-Capacity Clarification

Inspecting the 4.4-km Ganga river crossing connecting Bhagalpur with Navgachhia and the wider Kosi–Seemanchal belt, Engineer Kumar Shailendra examined slab, joint, and bearing work with Bridge Construction Corporation engineers and contractor representatives from SP Singla Construction Company. Addressing questions over whether heavy commercial vehicles would face permanent restrictions after the steel-truss rehabilitation, the minister stated clearly that the reconstructed spans are built to handle the same 70-ton load capacity as the original structure and will emerge stronger overall once finishing works wrap up. Alongside girder placement, crews have already replaced 20 of the 67 damaged expansion joints and are moving briskly through ball-bearing replacements.

January 30 Handover Target and Mandatory Load Test Before Traffic Resumes

In alignment with Chief Minister Samrat Chaudhary's timeline, teams are working toward completing and handing over the repaired bridge by January 30. However, Kumar Shailendra emphasized that passenger cars, buses, and freight trucks will not be allowed back onto the span immediately upon civil completion: engineers will first conduct a comprehensive full load test, and vehicular traffic will resume only after the structure clears every prescribed safety and strength benchmark.